Mozambique’s ENH takes an offshore drilling role at Coral North

Energy Africa · Independent reporting
Share

Eni and its partners have started drilling and completing development wells for Coral North, Mozambique’s second floating liquefied natural gas project. The campaign began on 1 November and is expected to last about 10 months. It is being carried out by ENH–Saipem Drilling Company using the Saipem 12000 drillship. Eni is targeting 2028 for start-up of the project, which will draw gas from the northern part of the Coral reservoir offshore Cabo Delgado.

The drilling contract gives Mozambique’s national hydrocarbons company, ENH, two roles in Coral North. It holds 10% of the project joint venture and participates in the company carrying out the drilling campaign. Eni described the arrangement as the first direct operating role in offshore drilling for a company with Mozambican participation. Eni holds 50% of the project venture, China National Petroleum Corporation holds 20%, and ENH, KOGAS and XRG each hold 10%.

Work on the floating plant is proceeding alongside the offshore campaign. The partners launched the hull in Geoje, South Korea, in January. The vessel is designed to process and liquefy 3.6 million tonnes of gas a year. The wells and the floating facility have separate construction schedules, but both have to be ready for start-up. The wells must be completed and connected. The vessel must be outfitted, positioned offshore and tested before it can accept gas for processing.

Coral South gives the partners an operating precedent in the same reservoir. It began production in 2022, and Eni said in its November update that it had delivered more than 175 LNG cargoes. The company expects Coral North and Coral South together to bring Mozambique’s liquefaction capacity to more than seven million tonnes a year. Actual exports will depend on how quickly Coral North ramps up and how consistently the two floating plants operate.

For the Mozambican services industry, the work to watch is how the drilling venture delivers the campaign. The approach gives a company with local participation responsibility for a defined offshore operation while the floating plant is built abroad. The distinction matters when assessing the economic contribution of the project. Some of the activity is tied to gas ownership and future exports. The drilling campaign provides earlier evidence of where operating responsibility is being placed and how Mozambican entities participate before production begins.

The investment decision was taken in October 2025. The November announcement moves the well programme into execution and provides a timetable against which to judge progress. Completion of the campaign and delivery of the floating facility are the next milestones before offshore commissioning. Eni’s 2028 target remains the date to watch for start-up.

admin

Related coverage

Watch Energy Africa

How to connect your VPS with Server Compass (No SSH knowledge)

Open on YouTube ↗

Search Energy Africa

ENERGY AFRICA

Choose your language

Choisissez votre langue

English →Français →