Tanzania sets phased energisation schedule for the TAZA power corridor

Tanzania’s electricity utility has set out plans to energise sections of its 400 kV corridor towards Zambia. In November, TANESCO said the project was about 95% complete and expected to begin switching on Dodoma–Iringa and Iringa–Kisada from 26 November. It scheduled Mbeya–Sumbawanga for 29 November. As of 28 November, the public updates reviewed set out the sequence, with completion of the individual switching operations still to be confirmed
The Tanzania–Zambia transmission project, known as TAZA, includes about 620 kilometres of line on the Tanzanian route, a connection towards Zambia at Tunduma and a branch towards Sumbawanga. TANESCO described Dodoma as a hub for routing electricity received from the Julius Nyerere hydropower plant via Chalinze. The investment therefore has a domestic purpose while the cross-border link develops
Switching on the line in stages allows TANESCO to check the equipment at each end and verify that protection and controls work before extending the sequence. The utility had scheduled interruptions in 11 regions on 14 and 15 November for work associated with the Dodoma upgrade. Modifying a substation that already supplies several regions requires coordination with other parts of the network, including the routes that carry electricity while equipment is taken out of service.
TANESCO expected Sumbawanga to start receiving electricity from the Tanzanian national grid by 5 December. That would reduce the town’s reliance on power imported from Zambia. The timetable for full cross-border operation is longer. The Zambian government told parliament in November that it expected commissioning of the full interconnector in the second quarter of 2029, according to Enerdata. The link is intended to connect the Southern and Eastern African power pools.
The first evidence for Sumbawanga will be confirmation that it has transferred to the Tanzanian grid. Regional buyers will be looking for a date for cross-border operation and the amount of capacity available for trade. Those milestones can arrive years apart, even though they are part of the same corridor.
Related coverage

Zambia–Malawi interconnector advances with a defined US$43 million Zambian package
The World Bank has published a procurement plan for Zambia’s portion of a proposed electricity link with Malawi. The Zambian section covers…

La Tanzanie prévoit une mise sous tension progressive du corridor électrique TAZA
La compagnie tanzanienne TANESCO a présenté un calendrier de mise sous tension du corridor de 400 kV vers la Zambie. En novembre,…

Nigeria commissions Billiri substation and doubles high-voltage capacity at Gombe
Nigeria has commissioned a new transmission substation at Billiri and upgraded an existing one in Gombe, expanding the capacity available to carry…