Nigeria commissions Billiri substation and doubles high-voltage capacity at Gombe

Nigeria has commissioned a new transmission substation at Billiri and upgraded an existing one in Gombe, expanding the capacity available to carry electricity through the north-east. Power Minister Joseph Tegbe commissioned the facilities on 19 November. The World Bank-funded works add 120 MVA at Billiri and double transformation capacity at the 330/132 kV level in Gombe from 300 MVA to 600 MVA.
Billiri’s 132/33 kV station uses two 60 MVA transformers and connects to the existing Gombe–Zabana–Yola transmission line. The station lowers voltage so that electricity can be carried on local feeders. The Transmission Company of Nigeria (TCN) puts the equivalent active-power capacity at about 96 MW. The 120 MVA figure describes the transformer rating. The power available to customers will depend on upstream supply and the capacity of the circuits leaving the station.
At Gombe, the project added a 300 MVA transformer at the higher-voltage stage. A separate 100 MVA transformer replaced a 30 MVA unit at the 132/33 kV stage, raising capacity there from 150 MVA to 220 MVA. That second change increases the amount the station can hand off to the local distributor. TCN says it awarded the Gombe upgrade in June 2021 and completed the works in June 2026, before November’s formal commissioning.
TCN has asked Jos Electricity Distribution Company to draw more power through the new facilities. For businesses that depend on standby generators, the benefit will show up if the additional capacity reduces the frequency or length of interruptions. The distributor still has to allocate power to feeders that can carry it. A constrained outgoing line or local transformer can limit what reaches customers even after the main substation is reinforced.
The next figures to watch are the load carried by the new transformers and the hours of supply on the outgoing feeders. They would show where the investment has relieved a bottleneck and where distribution work is still needed to make use of the added capacity.
Related coverage

Zambia–Malawi interconnector advances with a defined US$43 million Zambian package
The World Bank has published a procurement plan for Zambia’s portion of a proposed electricity link with Malawi. The Zambian section covers…

Tanzania sets phased energisation schedule for the TAZA power corridor
Tanzania’s electricity utility has set out plans to energise sections of its 400 kV corridor towards Zambia. In November, TANESCO said the…

La Tanzanie prévoit une mise sous tension progressive du corridor électrique TAZA
La compagnie tanzanienne TANESCO a présenté un calendrier de mise sous tension du corridor de 400 kV vers la Zambie. En novembre,…