Jindal signs first loan for Botswana’s Mmamabula power project

Jindal Power has signed a loan of approximately US$500 million for the Mmamabula coal power project in Botswana, according to its transaction adviser JSA. The firm named Axis Bank, ICICI Bank and the Export-Import Bank of India in its 17 November disclosure. Jindal expects to raise roughly another US$500 million in the coming months under a financing plan covering two phases of development. newserver.jsalaw.com
The two phases have different intended customers. Jindal describes a first 350 MW phase designed to supply state utility Botswana Power Corporation, followed by another 350 MW aimed at regional demand. The second phase is intended to support exports through the Southern African Power Pool. Regional grid access would make those sales possible, while the revenue available to the project would depend on the buyers, delivery terms and capacity to move electricity across borders. www.jindalpower.com
The public figures for the plant need to be read in context. Jindal describes Mmamabula as a 700 MW net project and lists December 2026 as a commissioning target. Botswana’s national climate submission retains 600 MW in its power-sector planning. In February, the government told parliament it expected the first 150 MW by December 2026 and the full 600 MW by June 2029. The published documents do not reconcile the sponsor’s project figure with the government’s planning figure. The first confirmed delivery will be the clearest near-term measure of progress. www.jindalpower.com
For Botswana Power Corporation, the project comes as the utility is seeking higher tariffs. In November, the regulator opened a consultation on BPC’s proposed average increase of 33% for the 2027–28 financial year. The application cites pressure from electricity import costs and the gap between the cost of supply and tariffs charged to several customer groups. Comments are due on 11 December. The regulator has yet to make its determination. bera.co.bw
Additional domestic generation could reduce the utility’s exposure to imported power when the plant is available. The financial effect will depend on the price BPC pays for Mmamabula’s electricity, the volume it must take and how much purchased power the new units can replace. The financing announcement does not set out those contract terms. Botswana is also working on the rehabilitation of Morupule B, another factor that will affect the utility’s need for imports. newserver.jsalaw.com
The next milestones are the amount of capacity actually delivered to BPC and the signing of the remaining debt. The first shows whether Mmamabula can begin contributing to Botswana’s power supply on the timetable presented to parliament. The second will show whether Jindal can complete the financing it has outlined for the project’s wider development.
Related coverage

AfDB backs US$125 million fundraising drive for distributed energy
A solar distributor can deliver a system today and collect the price in monthly instalments. While those payments come in, the distributor…

Ilikwa solar expansion reaches financial close with five- to ten-year power deals
The second phase of the Ilikwa solar plant near Parys reached financial close in November with a feature that matters to South…

FMO weighs €146.5 million debt package for Senegal’s Tamba Solar
Nearly two years after signing a power purchase agreement with Senegal’s national utility, Tamba Solar is seeking long-term debt for its project…