LE POINT SUR L’ÉNERGIE ET LES INFRASTRUCTURES EN AFRIQUE
LE POINT ÉNERGIEJournalisme indépendant · Énergie. Électricité. Infrastructures.dimanche, 29 novembre 2026

Gabon’s Kinguélé Aval begins final tests after connection to Libreville’s grid

Energy Africa · Journalisme indépendant
Partager

The substation serving Gabon’s 35 MW Kinguélé Aval hydropower plant has been connected to the 225 kV line feeding Libreville’s grid. Gabonreview reported the connection on 20 November, citing Gabon Power Company. Integrated testing was underway, and the developer expected first electricity in December, with the full 35 MW targeted by year-end. The connection gives the plant a route to market. The next milestone is power delivered through that connection.

For households and businesses in Greater Libreville, the connection works came with an immediate cost. Taking the line temporarily out of service reduced available capacity from the existing Kinguélé and Tchimbélé dams from 94 MW to 55 MW, according to the presidency. The resulting 39 MW reduction prompted President Brice Clotaire Oligui Nguema to call for a daily, neighbourhood-by-neighbourhood schedule of outages so customers could plan around the interruptions.

The work explains why the project’s first electricity matters more to Libreville than the percentage of construction completed. Gabon Power Company reported progress above 95% at the end of October. The remaining work included connecting the plant to the existing line and proving that the substation, controls and generating units could operate together. The energy minister had indicated first output at the end of November. The developer’s later update pointed to December. The plant’s three turbines are expected to enter service progressively.

Kinguélé Aval is being delivered by Asonha Energie, owned 60% by Meridiam and 40% by Gabon Power Company. At financial close in 2021, the sponsors put the project’s funding requirement at €179 million, about US$212 million at the time. The power plant is being developed under a 30-year concession. The International Finance Corporation’s project disclosure identifies the Gabonese government as buyer of the plant’s output under a power purchase agreement of the same duration.

The plant sits on the Mbei River, downstream of two existing hydro stations. At financial close, Meridiam expected it to supply up to 205 GWh annually. That estimate gives a sense of the project’s contribution over a year. In the first weeks, the more useful measure for the utility will be how much generation each turbine can deliver consistently after testing and how that output fits with supply from the existing dams.

Gabon is also adding thermal capacity to support Greater Libreville. As the two programmes progress, the immediate question for customers is whether the new units translate into fewer interruptions. At Kinguélé Aval, that starts with confirmation of first power, followed by the dates on which the remaining turbines become available to the grid.

admin

Sur le même sujet

Regarder Energy Africa

How to connect your VPS with Server Compass (No SSH knowledge)

Ouvrir sur YouTube ↗

Rechercher sur Energy Africa

ENERGY AFRICA

Choose your language

Choisissez votre langue

English →Français →